“We are chugging away at the site! The Harris Teeter pad, as you can see, is approximately 60% complete. The majority of the garage has been excavated and footings will start being formed next week. We will be prepared for the massive 3D puzzle that is the parking deck to start coming to the site in May for assembly.
 
The Church Street Apartment Building has continued to progress. Footings, masonry, and underground plumbing will all be underway next week.”
 